Category Archives: PMP Exam Question Practice

PMP Practice Exam Questions and Answers | 19

– See all the PMP Exam Questions – 

PMP Exam Practice Questions 19PMP Exam Question Session 19

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

A vendor is hired for your project and will charge you $30 per hour, plus materials. What is this type of contract called?

A)  Cost plus fixed fee
B)  Time and materials
C)  Task and materials
D)  Cost plus incentive fee

Question 2

Your project has had most of its products delivered by a third party. The project sponsor who will own these products in their functional area is not happy with the resulting products. The vendor believes they are suitable. What process will you go through to arrange a suitable outcome for both parties?

A)  Quality Administration
B)  Contract Administration
C)  Project Administration
D)  Claims Administration

Question 3

You are working within the procurement department of a company and a project has approached you for a template for formal documents they can use to collect information, quotes or proposals from potential vendors. What are these documents called?

A)  Bid Documents
B)  Vendor Documents
C)  Audit Documents
D)  Advertising Documents

Question 4

As a project manager you are aware that communication can become more complex, the more people there are to communicate to. How many different communication channels would there be with a project team of 19 people?

A)  380
B)  190
C)  171
D)  19

Question 5

You are working on a project with many different stakeholders and it is vital to communicate project updates early and often. What is the best type of communication method for passing information to stakeholders?

A)  Telephone
B)  Face to face
C)  Emails
D)  Formal report

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 21

– See all the PMP Exam Questions – 

PMP Exam Question Session 21

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You are working as a project manager with a business analyst and a tester on your team. You need to rank the issues occurring during testing from the most occurring to the least occurring, to see where to focus on first. What will you use?

A)  Control chart
B)  Pareto Diagram
C)  Flow Chart
D)  Check Sheet

Question 2

You are working through the quality management process of a project in the finance sector, and need to select the most appropriate option from a variety of options. What technique will you use?

A)  Group activities
B)  Agreements
C)  Decision Making
D)  Meetings

Question 3

You are working with a project manager in the Quality area of a project, with the aim of improving the end to end life-cycle of the project’s development. You will need to identify the problem, discover the underlying causes that lead to it, and develop preventive actions. What is this called?

A)  Flow chart Analysis
B)  Root Cause Analysis
C)  Risk Cause Analysis
D)  Corrective Analysis

Question 4

What would be the total of the Cost Plus Fixed Fee (CPFF) type of contract with a target cost of $421,000 plus a fixed fee of $45,000, if the project actual spent costs at the end is $251,000?

A)  $45,000
B)  $421,000
C)  $296,000
D)  $121,000

Question 5

You are working with a third party vendor to deliver a part of your project, and needing to ensure they will deliver what you need and on time. Price has been agreed, but other things are still to be negotiated. Which of the following is one of the items that can be negotiated as part of a procurement contract?

A)  The type of software used
B)  Your bonus
C)  Size of the project
D)  Project Management process to be used

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 18

– See all the PMP Exam Questions – 

PMP Practice Exam Questions 18PMP Exam Question Session 18

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You would like to motivate and align your team towards the project goals using a team building activity. Which of the following is one of the types of Team Building Activities?

A)  Performing repetitive tasks
B)  Following the agenda
C)  Documenting meeting minutes
D)  Creating the WBS

Question 2

Interpersonal Skills have the power to directly or indirectly impact the outcome of a project. Which of the following is NOT one of the types of Interpersonal Skills a project manager might use?

A)  Leadership
B)  Creating a scatter plot
C)  Team building
D)  Motivation

Question 3

You are working on a project and need to create a document that has compiled information about project performance in a report format to enable decisions, actions and project communications?

A)  Work Performance Report
B)  Project Management Plan
C)  Agreements
D)  Verified deliverables

Question 4

Your project needs to hire resources from outside the organisation, and the vendor has provided a Cost Plus Fixed Fee (CPFF) type of contract with a target cost of $280,000 plus a fixed fee of $29,000. What is the total cost if the project costs at the end is $250,000?

A)  $309,000
B)  $280,000
C)  $279,000
D)  $149,000

Question 5

You are a project manager working in a company and you have been asked to compile the business case and benefits management plan. What are these types of documents called?

A)  Executive Documents
B)  Business Documents
C)  Project Documents
D)  Project Charter

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 17

– See all the PMP Exam Questions – 

PMP Practice Exam Questions 17PMP Exam Question Session 17

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

Estimate at Completion is the forecasted cost of the project as the project progresses. Your project has a budget of $10,000.
30% of the work has been completed against planned 30%, and $10,000 has been spent so far. If the CPI impacts our future cost, what is the Estimate At Completion (EAC)?

A)  $17,000
B)  $44,444
C)  $33,333
D)  $22,222

Question 2

You are working on a project and wanting to plan the immediate work in detail, while leaving the remaining work at a higher level. What are you doing?

A)  Executive Planning
B)  Rolling Wave Planning
C)  Progressive Planning
D)  Extra Planning

Question 3

You are working with your project team and wanting to stimulate creativity and new ideas. Which of the following is a group creativity technique you might use?

A)  Nominal group technique
B)  Regression analysis
C)  Tornado diagram
D)  Prompt lists

Question 4

As a project manager, you are wanting to work with the project sponsor to bring more objectivity to the acceptance process. What is this project activity called?

A)  Collecting Requirements
B)  Estimating Activity Durations
C)  Planning Schedule Management
D)  Validating Scope

Question 5

You are working through the scope of your project and wanting to decompose the high level features into smaller pieces of work that a team can deliver using a work breakdown structure. What is that level of the work breakdown structure called?

A)  Work Package
B)  Work Product
C)  Work Deliverable
D)  Work Task

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 16

– See all the PMP Exam Questions – 

PMP Exam Question Practice 16PMP Exam Question Session 16

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You are working on a major project for your company, where only 50% of the project has been completed, while 80% of the project budget has been spent. When making a decision on whether or not to continue, what are the costs called that have already been spent?

A)  Earned Value
B)  Exception Report
C)  Sunk Costs
D)  Milestone

Question 2

The To Complete Performance Index (TCPI) is the future cost performance of the project. Your project has a budget of $15,000. 50% of the work has been completed, against planned 60%. $9,000 has been spent so far. What is the efficiency that must be maintained in order to complete as planned (TCPI)?

A)  1.89
B)  1.25
C)  0.56
D)  0.78

Question 3

Your project has a budget of $200,000.
60% of the work has been completed against planned 50%. $590,000 has been spent so far. What is the Schedule Performance Index (SPI)?

A)  1.20
B)  0.83
C)  0.63
D)  2.50

Question 4

You are working on a brand new project and need to estimate how much it will cost. You have the cost per unit for all items needed. What is the name of the estimating technique you will use?

A)  Three point estimating
B)  Executive estimating
C)  Data estimating
D)  Parametric estimating

Question 5

Your project has a budget of $500,000. 60% of the work has been completed against planned 70%. $280,000 has been spent so far. What is the Earned Value (EV)?

A)  $500,000
B)  $280,000
C)  $300,000
D)  $350,000

– See all the PMP Exam Questions – 

PMP Exam Questions – Practice Session | 15

– See all the PMP Exam Questions – 

PMP Exam Question Practice 15PMP Exam Question Session 15

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

You are working through various options in your project and need to help stimulate your group towards innovation and ideas. Which of the following is a type of group creativity technique?

A)  Monte Carlo Analysis
B)  Regression analysis
C)  Brainstorming
D)  Root cause analysis

Question 2

You are working as a project manager, at the stage where you need to validate the scope and products you have created with the appropriate people. What is the output called that is produced by a project and approved by the end-user or customer?

A)  Accepted Products
B)  Accepted Deliverables
C)  Accepted Results
D)  Accepted Data

Question 3

You are working on your Project Management Plan and will need the opinion of an individual or a group who has a wide range of knowledge and experience in that specific field. What is this called?

A)  Expert Judgment
B)  Expert Findings
C)  Expert Comment
D)  Expert Decision

Question 4

You are developing a new product and decide to add three extra features that the customer did not ask for, to make the product extra special. You feel as though it will work better this way. What is this called?

A)  Scope Creep
B)  Customer first
C)  Verified Deliverables
D)  Gold Plating

Question 5

A project management plan is a formal approved document that defines how the project is planned, executed, monitored and controlled. Who is responsible for creating and updating the project management plan?

A)  The Program Manager
B)  The Project Manager
C)  The Project Sponsor
D)  The Project Team

– See all the PMP Exam Questions – 

PMP Exam Questions – Practice Session | 14

– See all the PMP Exam Questions – 

PMP Exam Question Practice 14PMP Exam Question Session 14

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

You are working on a project and have been asked to create a plan that shows the practices and procedures to be adopted for execution and monitoring and controlling the project. What will you create?

A)  Risk Management Plan
B)  Project Management Plan
C)  Sponsor Management Plan
D)  Benefits Measurement Plan

Question 2

You have recently discovered the importance of communication in your project after one of your directions was misunderstood. What is one of the most effective way to handle complex communications?

A)  Informal written communication
B)  Oral formal communication
C)  Formal written communication
D)  Oral informal communication

Question 3

You are working in the risk area of a project. The project work is half way complete and dozens of new risks have been found that could jeopardise your project. The risk plan is not yet complete. When should risk management planning have been completed?

A)  At the beginning of your project, during initiation and planning
B)  In the middle of your project, during execution
C)  When monitoring your project – you can analyse what isn’t created yet
D)  When the project is finalised – as you will know the risks that have occurred.

Question 4

You are a project manager needing to use a project tool and technique that will inspect, clean, transform and model large amounts of data to uncover the impact of certain project risks. What technique are you using?

A)  Meetings
B)  Assessment Analysis
C)  Information Technology
D)  Data Analysis

Question 5

You are working on Risk Planning in your project and have asked one of your team to find the established records of risk categories within the organisation for you to pick from and re-use. What project management tool and technique are these also called?

A) Prompt Lists
B)  Mitigation Lists
C)  Issue Lists
D)  Risks Lists

– See all the PMP Exam Questions – 

PMP Exam Questions – Practice Session | 13

– See all the PMP Exam Questions – 

PMP Exam Question Practice 13PMP Exam Question Session 13

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

You have started to notice the impact that team motivation has on your project results. If you are giving your team love, affection, acceptance, friendship, you are using their:

A)  Legal Needs
B)  Social Needs
C)  Wealth Needs
D)  Organisational Needs

Question 2

You are working on a project where a strict and powerful union for the employees ensures that no employee can work more than 37 hours a week. This is an example of:

A)  Project permissions
B)  Project regulations
C)  Project constraints
D)  Project laws

Question 3

You are working on an Agile project and have been asked to create a document that lists team principles, agreements, and guidelines about the acceptable behaviour by team members. What are you working on?

A)  The Team Guideline
B)  The Project Management Plan
C)  The Project Charter
D)  The Team Charter

Question 4

You are managing a project team and need to ensure your team members are doing what is needed to get the job done. What is a project document you will use that helps you know the effectiveness of the team?

A)  Team Performance Assessments
B)  Team Progress Assessments
C)  Team Presentation Assessments
D)  Team Achievement Assessments

Question 5

A project manager will spend up to 90% of their time communicating, and your interpersonal skills will directly or indirectly impact the outcome of your project. Which of the following is a type of interpersonal skill?

A)  Selling
B)  Converting
C)  Team building
D)  Physical skills

– See all the PMP Exam Questions – 

PMP Exam Questions – Practice Session | 12

– See all the PMP Exam Questions – 

PMP Exam Question Practice 12PMP Exam Question Session 12

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

You have been asked to prepare a document to gain the project sponsor’s sign off to access their function’s resources, that details the project goal and business case, high-level scope and requirements, high level dates and milestones, a high-level budget, and initial risk analysis. What are you creating?

A)  Project Management Plan
B)  Project Charter
C)  Risk Management Plan
D)  Lessons Learned

Question 2

You are working with the quality assurance manager of your project, where they are using a fishbone diagram to perform a cause and effect analysis for a problem you are working on to solve. What else is a fishbone diagram called?

A)  Ishikawa Diagram
B)  Value Stream Map
C)  Pareto Diagram
D)  Control Chart

Question 3

You are working in the quality assurance and testing phase of your project, where the test manager makes use of many different ways to assess project quality control. Who has the most responsibility for project quality control?

A)  The vendor
B)  The functional manager
C)  The project manager
D)  The project sponsor

Question 4

Your quality assurance manager on your project is using a technique in order to validate the scope and gain sign off on the deliverables. What is it called when they check the quality of the product against the quality requirements?

A)  Checking
B)  Assessment
C)  Evaluation
D)  Inspection

Question 5

You have noticed your project team starting to drift off, miss deadlines and make quality defects, and decide to learn a skill that will help bring the team together again. What will you research for information on how people, teams, and organizational units function in a project?

A)  Organizational Process Assets
B)  Organizational Theory
C)  Organizational Charts
D)  Organizational Structure

– See all the PMP Exam Questions – 

PMP Exam Questions – Practice Session | 11

– See all the PMP Exam Questions – 

PMP Exam Practice Questions 11PMP Exam Question Session 11

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

You are working as a project manager and you need a source of information and knowledge on a product to ensure project success. You recognise this as “Expert Judgement” from the PMBOK Guide. What is the first place you should look for expert judgment?

A)  The vendor’s organization
B)  Hire someone outside your organization
C)  Your own organization
D)  Ask the Government

Question 2

Planned Value is the dollar value of the work you have planned to have completed at a given time in your project. Your project has a budget of $10,000. 40% of the work has been completed against planned 30%, and $14,000 has been spent so far. What is the Planned Value (PV)?

A)  $700
B)  $1,200
C)  $200
D)  $3,000

Question 3

You have been asked to use an estimation technique that uses data from past projects to budget for an activity that is very similar in nature and duration. What is this type of estimating technique?

A)  Corresponding Estimating
B)  Analogous Estimating
C)   Parallel Estimating
D)   Symmetrical Estimating

Question 4

You are working on a project with a budget of $10,000. 30% of the work has been completed against planned 40%. $15,000 has been spent so far. What is the Estimate at Completion (EAC), if the CPI is expected to be the same?

A)  $50,000
B)  $15,000
C)  $150,000
D)  $45,000

Question 5

You are working on a project with a budget of $10,000, where 50% of the work has been completed, against a planned 40%.  $7,000 has been spent so far. What is the Schedule Performance Index (SPI)?

A)  1.25
B)  1.39
C)  2.43
D)  0.74

– See all the PMP Exam Questions –