PMBOK 8th Edition Practice Questions 51 to 60 – Pass your PMP and Learn the PMBOK Guide

We use the PMP Fast Track to answer PMP questions quickly and easily. Check it out!

Question 51 – Organizing Deliverables Into Manageable Components

A product development team needs to clearly organize all deliverables and decompose the work into manageable components to support planning and execution. What should the project manager do next?

Question 52 – Adding More Detail to Work Packages

A project manager has elicited requirements and turned them into project scope. He now wants to add more detail to the work packages to ensure clarity and alignment across the team. What should he do next?

Question 53 – Stakeholders Requesting More Information on Quality Issues

During monitoring, inconsistencies in deliverable quality are identified on a pharmaceutical project. Stakeholders request additional information on these issues to support improvements. What should the project manager produce?

Question 54 – Client Reviewing Outputs for Formal Approval

Several completed components have passed internal quality checks on a bridge construction project. The client is now reviewing outputs against agreed criteria to determine formal approval. What should the project manager obtain as an input to support the client’s decision?

Question 55 – Leadership Concerned About How Schedule Decisions Are Being Made

Leadership expresses concern about how schedule decisions are being made and controlled throughout a nationwide fiber network project. What should the project manager do next?

Question 56 – Leaders Want to See the Plan for Managing the Schedule

Business leaders want to see the plan for managing the schedule on a security project. What does the project manager need to know before creating the schedule management plan?

Question 57 – Stakeholders Approve the Final Schedule

After multiple iterations analyzing sequence, durations and resources, stakeholders approve the final schedule on a core banking upgrade. What should the project manager do next?

Question 58 – Same Engineer Needed for Overlapping Critical Activities

Several critical activities require the same specialized engineer at overlapping times, creating unrealistic workload expectations and risking delays. What should the project manager do?

Question 59 – Near-Term Work Is Clear but Future Work Is Uncertain

A team struggles to finalize the schedule because near-term requirements are clear but work planned for later is uncertain due to evolving requirements. There is pressure to begin quickly. What should the project manager do?

Question 60 – Packaging, Labelling and Inspection With Specific Timing Dependencies

Packaging design must be finalized before mass production, labelling can begin once initial drafts are approved and quality inspection must wait two days after production finishes. What should the project manager do next?

Pep Talk

Sixty questions down and you are working through scope and schedule in the PMBOK Guide. The questions keep getting trickier and so does your understanding. Keep going.

– David McLachlan

You can see what people are saying about David McLachlan here: REVIEWS

Navigate to Free Project Management and Leadership Articles through the links on the right (or at the bottom if on Mobile) 

PMI PMP 35 PDUs CourseThe Ultimate PMP Project Management Prep Course (35 PDUs)
Agile Certified Practitioner (PMI-ACP 28 PDUs)The Complete PMI-ACP Course: (28 PDUs) 
PgMP Program Management CourseLearn Program Management – the PgMP Prep Course
Full PMP Exams to Pass on the First TryFour Full PMP Practice Exams (180 Qs each) to pass your PMP on the First Try!
Scrum Master Course PSMScrum Master Course (PSM)
Product Owner Course PSPOProduct Owner Course (PSPO)
Business Analyst CourseBusiness Analyst Course

Also available are my Project Management Templates – they’re a great way to save 100s of hours when you’re first starting out:

50 Project Management Templates Gantt Chart Risk Matrix and more Excel50+ Project Management Templates in Excel and PowerPoint (Gantt Chart, Risk Matrix and more!)
Project Management Plan TemplatesPre-made Project Management Plan Templates: Save 100 HOURS!

 

Leave a Reply

Your email address will not be published. Required fields are marked *