We use the PMP Fast Track to answer PMP questions quickly and easily. Check it out!
Question 61 – Reviewing Schedule Performance With a Basis for Interpreting Results
A project manager monitors schedule performance and sees differences that might require action. She has a basis for interpreting the current results. What should she use to make the required decisions?
Question 62 – Multiple Sequencing Scenarios With No Agreement on the Best Path
A complex project has multiple parallel activities competing for limited scheduling options. Delays are emerging and the team cannot agree on the best sequencing approach. How should the project manager proceed?
Question 63 – Completion Date Moved Earlier With No Budget Increase
A hospital construction project has its completion date moved earlier but the budget cannot be increased. Several activities could overlap. What approach should the project manager apply to shorten the timeline?
Question 64 – Team Asking How Financial Activities Will Be Handled
During early planning, the team raises questions about how financial activities will be handled, including acceptable estimate ranges and triggers for escalation. What should the project manager show them?
Question 65 – Finalizing the Financial Plan With Interest From External Organizations
A project manager is finalizing the plan to manage finances on a carbon capture project. Large organizations with significant interest in the project outcomes are identified. What should she do next?
Question 66 – Quick Estimate Needed With Limited Information
A project manager needs a quick estimate to support early planning discussions. Detailed information is limited but a senior team member has worked on a similar project before. What estimating approach should be used?
Question 67 – Products Returned by Customers Due to Defects
After product release, several units are returned due to defects requiring repairs and replacements. The project manager needs to categorize these costs within quality-related expenses. What type of cost is this?
Question 68 – Potential Soil Instability Identified During Planning
A team identifies potential soil instability during planning that may require additional foundation work. The sponsor wants to handle the uncertainty without inflating the budget unnecessarily. What should the project manager do?
Question 69 – Individual Cost Estimates Developed but No Single Approved Budget Yet
Cost estimates have been developed for individual activities and a single approved version of the budget is now needed to track and measure future performance. What should the project manager do first?
Question 70 – Senior Leaders Question the Accuracy of Cost Estimates
Cost estimates for individual work packages have been completed but senior leaders question their accuracy and are concerned about project delivery. What should the project manager do next?
Pep Talk
Seventy questions down and you are working through schedule control and financial management in the PMBOK Guide. Every question builds the knowledge you need for exam day. Keep going!
– David McLachlan
You can see what people are saying about David McLachlan here: REVIEWS
Navigate to Free Project Management and Leadership Articles through the links on the right (or at the bottom if on Mobile)
Also available are my Project Management Templates – they’re a great way to save 100s of hours when you’re first starting out:
50+ Project Management Templates in Excel and PowerPoint (Gantt Chart, Risk Matrix and more!) |
Pre-made Project Management Plan Templates: Save 100 HOURS! |





